"The midway cross walk in front of Cherry Republic is not safe."
That line comes from one of nearly 400 responses to the Michigan Department of Transportation's online survey about downtown Charlevoix. The survey ran in November and December 2025 and closed on January 1, 2026. The crossing that comment describes, the unsignalized one at Van Pelt Alley, is scheduled to close. It is one piece of a $2 million package that rebuilds how people on foot and in cars share US-31 through downtown.
The paperwork is further along than most people realize. MDOT advertised the job on August 28, 2026, and scheduled the bid letting for October 2, 2026. The ad describes "closing and adding crossings, concrete sidewalk ramps, bump outs, signing, pavement markings and signal work at 4 locations on US-31 from Antrim Street to Meech Street." Its listed completion date is June 18, 2027.
Under the plan, downtown trades the freedom to cross almost anywhere for signals that give everyone a regular, predictable turn. One thing stays as it is: the drawbridge. It causes much of the waiting, and it runs on a federal schedule that this project doesn't touch.
Every crossing moves to a light
MDOT's explanation starts from a problem everyone on Bridge Street has felt from both sides. "Drivers are frustrated and slowed when pedestrians cross wherever is convenient for them, and pedestrians feel there are not enough safe and convenient crossings on US-31 (Bridge Street)," the department wrote on its project page.
Its answer is to put the crossings where the signals are, and add signals where people need to cross. Here is how the plan changes the main spots on Bridge Street, as MDOT describes them:
| Location | Today | Under the 2027 plan |
|---|---|---|
| Antrim Street | No signal | New traffic signal with pedestrian crossing signals |
| Mason Street | Signalized intersection | New signal with crossing signals; Mason becomes one-way westbound |
| Clinton Street | Signalized crossing nearby | Gains the relocated Van Pelt crossing on its north side; Clinton becomes one-way eastbound |
| Van Pelt Alley | Unsignalized mid-block crossing | Closed |
| Park Avenue | No signal | New traffic signal with crossing signals |
| South side of the bascule bridge | Crosswalk | Closed and moved to the new Park Avenue signal |
| North side of the bascule bridge | Crossing | Improved pedestrian crossing |
The Top of Michigan Trails Council's summary of the plan also mentions curb bump-outs, which match the "bump outs" in the bid ad.
"We're looking to introduce new traffic signals at three locations downtown to give people a safe and convenient place to cross, removing some of the unsignalized crossings, and coordinating those movements so that we get improved traffic flow and improved safety," MDOT communications representative James Lake told UpNorthLive after the March 4, 2026 open house.
The word that matters there is "coordinating." MDOT says the changes "would require the proposed changes to be implemented together, as their benefits are interdependent and won't work as well, or possibly at all, if not put in place holistically." If the Van Pelt crossing closed without a light at Clinton, people would just walk farther. If Antrim and Park got lights without the side streets changing, turning traffic could still back up at Mason. MDOT is treating the whole stretch from Antrim to the bridge as one connected system.
There's local precedent for that approach. MDOT credits the 2018 conversion of Bridge Street from four lanes to three with "a more than 50 percent reduction in crashes." That change also reshaped the whole road at once, and the department plainly sees it as the model here.
The side streets change direction too
Of all the changes, the one-way conversions are most likely to change how locals drive. Mason Street becomes one-way westbound and Clinton Street becomes one-way eastbound. MDOT says the goal is to "reduce congestion and delays at these intersections and improve traffic flow."
In practice, any trip that now runs east on Mason will need a different route, and so will any trip that runs west on Clinton. Fewer directions at those two intersections means fewer turning movements for the new signals to handle. That ties back to the survey: one recurring complaint was "Needing longer green time at Mason Street/US-31 (Bridge Street) traffic signal," and another was "No left-turn lane on northbound US-31 at Antrim Street." MDOT hasn't published signal timing, so whether Mason gets more green time is still unknown.
At least one survey respondent wanted to go further and make Park, Mason and Antrim all one-way "from Bridge St to Antrim St," to cut down on turns off Bridge Street. The final plan converts two streets instead, on opposite sides of the downtown core and in opposite directions.
A crossing comes back at the north side of Clinton
The Clinton corner has a short history. When MDOT asked whether conditions had improved, most people said they had gotten worse, some adding words like "much," "way," "exponentially," and "significantly!" The minority who saw improvement gave credit to a few changes. One was the "removal of the north Bridge Street crosswalk at Clinton." The others were the cement flower-pot barriers and the three-lane conversion.
The 2027 plan puts a crossing back on the north side of the Clinton intersection, where it takes the place of the Van Pelt mid-block crossing. What's different is where it sits. MDOT says the move is meant to "reduce unexpected crossings at the mid-block crossing and encourage pedestrians to cross at the nearby signalized crossing." So the crossing returns at a signal instead of an unprotected spot. That fits the most common suggestion in the survey, which was to remove the Van Pelt crossing altogether.
Visibility was the complaint behind it. Among the most frequent comments was that some crosswalks "have poor visibility, particularly at the mid-block crossing at Van Pelt Alley." One respondent suggested that "to improve visibility for southbound traffic, the parking space at the northwest corner of the crosswalk" should be changed. MDOT's published list of changes doesn't mention removing any parking.
The bridge keeps its half-hour schedule
Survey respondents named the bascule bridge as a frequent source of delay, specifically "that the bascule bridge openings on the half-hour cause delays." Some said "more boat traffic resulting in more bridge openings" was part of why things felt worse. Limiting openings to once an hour was one of the most common suggestions.
The project doesn't include that change, because it isn't MDOT's to make on its own. The bridge carries US-31 over the Pine River, and its openings are governed by U.S. Coast Guard regulation 33 CFR 117.641. From April 1 through October 31, between 6 a.m. and 10 p.m., the bridge opens for recreational boats on a fixed window, "three minutes before to three minutes after the hour and half-hour." Public-safety, commercial and distressed vessels, and boats seeking shelter from severe weather, are passed as soon as possible. From April 1 through December 31, the bridge otherwise opens on signal. From January 1 through March 31, it opens on signal with at least 12 hours' advance notice.
The current schedule took effect in 2000. MDOT, which owns the bridge, requested it, and the Coast Guard's Ninth District changed the regulation. The federal code's own timeline for the section reads "No changes found for this content after 1/03/2017." Changing the lift schedule would take its own federal process, separate from this project.
That's why the new signals matter. The bridge will keep lifting on the hour and half-hour from spring through October. The plan's bet is that if lights at Park, Mason and Antrim control the downtown blocks, the line that builds up during each lift will clear faster than it does now. MDOT's stated aim is "regular and predictable opportunities for drivers to proceed." The new crossing south of the bridge will be at the Park Avenue light, which puts people on foot on the same timed cycle as cars.
What the calendar shows, and what it leaves open
MDOT gives the project schedule as "Spring 2027." The bid ad's completion date of June 18, 2027 means the contract work is set to finish before the busiest weeks of summer. MDOT's published materials don't say how the work will be phased, where detours will go, or how construction will work around early-season events.
The city has a role on paper. The Charlevoix City Council's September 21, 2026 agenda included an item titled "MDOT Highway Repair Contract On US 31," with a staff report and a bid tab attached. The attachments weren't available to review, so it's unconfirmed that the item covers this project, and so is how the council acted on it. The $2 million figure is MDOT's published project cost. It is not a winning bid.
For lane closures once work starts, MDOT points drivers to its Mi Drive map, which shows active construction zones. The full plan, survey summary and public comments are on MDOT's US-31 Charlevoix project page and its project FAQ.
At Pat O'Brien & Associates, our Charlevoix office will be following the work as it moves from bid to completion next spring. If you have questions about how the changes might affect your street or your property downtown, Contact Us. We're glad to talk it through.